PMP Q #17 – Establish Context
Q17. You are planning a kickoff meeting for a project; which of the following can help establish the project context?
A. Vision
B. Release Plan
C. Project Schedule
D. Project Scope Statement
Option A is the perfect match. Let’s see how –
If you plan a kickoff meeting, you are at the start of a project. At this stage, you need to establish the context of the project. Project vision helps set the context because a vision statement includes – a short product description, intended users, key desired objectives, and key features & directions.
Once you get a context based on the project approach (Agile or predictive), you proceed with the release plan, project schedule, and project scope statement.